91成人精品一区在线播放,成人毛片在线播放器,国产精品剧情av,日韩尤物在线,亚洲麻豆视频,岛国免费在线,亚洲a欧美

軟題庫(kù) 移動(dòng)APP 掃碼下載APP 隨時(shí)隨地移動(dòng)學(xué)習(xí) 培訓(xùn)課程
試卷名稱(chēng) 2017年信息系統(tǒng)項(xiàng)目管理師最新英語(yǔ)模擬題(5)
考試中心《2017年信息系統(tǒng)項(xiàng)目管理師最新英語(yǔ)模擬題(5)》在線考試
試卷年份2017年下半年
試題題型【單選題】
試題內(nèi)容

Although the stakeholders thought there was enough money in the budget, halfway through the project the cost performance index (CPI) is 0.7. To determine the root cause, several stakeholders audit the project and discover the project cost budget was estimated analogously. Although the activity estimates add up to the project estimate, the stakeholders think something was missing in how the estimate was completed. Which of the following describes what was missing?
A、Estimated costs should be used to measure CPI.
B、SPI should be used, not CPI.
C、Bottom-up estimating should have been used.
D、Past history was not taken into account.


相關(guān)試題

推薦文章