91成人精品一区在线播放,成人毛片在线播放器,国产精品剧情av,日韩尤物在线,亚洲麻豆视频,岛国免费在线,亚洲a欧美

軟題庫 移動APP 掃碼下載APP 隨時隨地移動學習 培訓課程
試卷名稱 2017年信息系統(tǒng)項目管理師最新英語模擬題(1)
考試中心《2017年信息系統(tǒng)項目管理師最新英語模擬題(1)》在線考試
試卷年份2017年下半年
試題題型【單選題】
試題內(nèi)容

During the execution phase of the project, the project team identified a serious project plan deviation. The scope of the project was defined correctly but the planning missed some technical deliverables that have impacted the schedule and the planned cost.In order to assure the success of the project, which should the project manager do?
A、Ask the customer to pay the cost of the deviation
B、Propose a change request, and inform the stakeholders of this case to get their supports
C、Negotiate with team to work overtime for mitigating the impact of cost and schedule
D、Negotiate with customer to reduce the scope of project for avoiding the deviation


相關試題

推薦文章
合作網(wǎng)站內(nèi)容