The project manager presents deliverables to the customer for approval. The customer claims that the deliverables do not meet the acceptance criteria, and asks the project manager to rework the deliverables. The customer also wants to access the information regarding the progress of the rework. Which activity should the project manager execute next ?
A、Configuration identification
B、Configuration status account
C、Configuration control
D、Configuration verification and audit