試卷名稱 2017年信息系統(tǒng)項目管理師最新英語模擬題(5)
考試中心《2017年信息系統(tǒng)項目管理師最新英語模擬題(5)》在線考試
試卷年份2017年下半年
試題題型【單選題】
試題內(nèi)容

During the Define Activities process, a team member begins to discuss activities that the project manager has never heard discussed. What should the project manager do?
A、Make sure he has a good understanding of the activities and include the activities in the activity list.
B、Ask the team member to explain why such an activity would be needed to complete the work package.
C、Make sure the entire team agrees that the activities should be don
D、Evaluate the impact of the change.