The project manager has just been assigned to manage a project in the middle of the execution phrase. The project has had a high turnover rate of project resources.What should the project manager do FIRST?
A、Organize a team-building event to improve team morale.
B、Talk to the project sponsor to get commitment for project resources.
C、Check the staffing management plan.
D、Move the most active team members to the same room to enhance their ability to perform as a team.