試題內容

A Team member was recently promoted as project manager and has been assigned a $2million. The department manager schedules a meeting to review the project charter within two weeks.What should the project manager do next?
A、Create the project scope statement.
B、Meet with the sponsor to define the business needs.
C、Schedule a kick-off meeting with team members.
D、Review the project management plans with the stakeholders.