試題內(nèi)容

During project execution, the customer indicates that there will be limited access to the test facility due to several concurrent projects. This change may lead to schedule delays. To minimize the negative impact, what should the project manager do next?
A、Advise the customer about schedule creep.
B、Check the risk register for approved corrective actions.
C、Perform a risk analysis.
D、Update the project schedule according to this change.