試卷名稱(chēng) 2017年信息系統(tǒng)項(xiàng)目管理師最新英語(yǔ)模擬題(4)
考試中心《2017年信息系統(tǒng)項(xiàng)目管理師最新英語(yǔ)模擬題(4)》在線(xiàn)考試
試卷年份2017年下半年
試題題型【單選題】
試題內(nèi)容

Project projections show that the project will fall behind in the testing phrase. This event was documented as a known risk at the project’s beginning due to the time to market imperative because the project is currently in the analysis phrase, the project manager decides to outsource the testing function and begin discussions with the chosen vendor.Of which risk strategy is this an example?
A、Avoidance
B、Transference
C、Sharing
D、Mitigation