91成人精品一区在线播放,成人毛片在线播放器,国产精品剧情av,日韩尤物在线,亚洲麻豆视频,岛国免费在线,亚洲a欧美

軟題庫(kù) 移動(dòng)APP 掃碼下載APP 隨時(shí)隨地移動(dòng)學(xué)習(xí) 培訓(xùn)課程
試卷名稱 2017年信息系統(tǒng)項(xiàng)目管理師最新英語(yǔ)模擬題(4)
考試中心《2017年信息系統(tǒng)項(xiàng)目管理師最新英語(yǔ)模擬題(4)》在線考試
試卷年份2017年下半年
試題題型【單選題】
試題內(nèi)容

A project manager discovers a key feature of the deliverable deviates from the customer’s original specification, but meets quality and legal requirements With budget and schedule constraints team members suggest keeping the original design. White other team members insist on modifying the design to meet the customer’s requirement. After negotiation, the final decision is to keep the current design.The project manager should take which of the following actions next?
A、Follow the risk response matrix
B、Change the quality plan
C、Update scope management plan
D、Follow the change management procedure


相關(guān)試題

推薦文章