試卷名稱(chēng) 2017年信息系統(tǒng)項(xiàng)目管理師最新英語(yǔ)模擬題(3)
考試中心《2017年信息系統(tǒng)項(xiàng)目管理師最新英語(yǔ)模擬題(3)》在線考試
試卷年份2017年下半年
試題題型【單選題】
試題內(nèi)容

A project manager presents the project plan to key stakeholders, citers stakeholder input, and obtains approvals. Later, a stakeholder says that a detail in the communications plan reeds to be changed, The project manager discusses it with stakeholder and they agree to the suggested changes.What should the project manager do next?
A、Create subsidiary documents in the communications management plan.
B、Generate a change request and submit it to the change control board.
C、Keep the project plan as it has been approved by stakeholders.
D、Change the communications plan and request stakeholders’ approval.