試卷名稱 信息系統(tǒng)項(xiàng)目管理師-pmp練習(xí)題-2
考試中心《信息系統(tǒng)項(xiàng)目管理師-pmp練習(xí)題-2》在線考試
試卷年份2017年下半年
試題題型【單選題】
試題內(nèi)容

The delivery of an inventory management system is being subcontracted based on the value of US$4,000,000. During deployment of the system, it cannot meet the quality requirements. The test needs extra time and money to be done. Which of the following process could contain additional testing and evaluation to provide US$20,000 ?
A、Risk Management Plan
B、Resource Management Plan
C、Change Management Plan
D、Quality management plan