試卷名稱 信息系統(tǒng)項目管理師-pmp練習題-2
考試中心《信息系統(tǒng)項目管理師-pmp練習題-2》在線考試
試卷年份2017年下半年
試題題型【單選題】
試題內(nèi)容

While the execution phase, the project team anticipates that the customer may request a new set of requirements. This is logged as a risk. Today, the customer formally gives notice that the new requirements are to be effective. What should the project manager's next step be ?
A、Update the risk register and create a change request.
B、 Execute the risk response plan associated with the risk.
C、 Update the risk register and the risk management plan.
D、 Adjust the schedule in accordance with the new requirements.