91成人精品一区在线播放,成人毛片在线播放器,国产精品剧情av,日韩尤物在线,亚洲麻豆视频,岛国免费在线,亚洲a欧美

軟題庫 移動APP 掃碼下載APP 隨時隨地移動學習 培訓課程
試卷名稱 信息系統(tǒng)項目管理師-pmp練習題-1
考試中心《信息系統(tǒng)項目管理師-pmp練習題-1》在線考試
試卷年份2017年下半年
試題題型【單選題】
試題內(nèi)容

At a project status team meeting, one team member disagrees with another team member regarding a corrective action. The debate escalates and they are soon both adamantly, Other team members are not participating. The project manager directs the team on the corrective action to use.  What conflict resolution technique did the project manager use ?
A、Compromising
B、Forcing
C、Withdrawing
D、Smoothing


相關試題

推薦文章
合作網(wǎng)站內(nèi)容