試題題型【單選題】
試題內(nèi)容

Several of the key stakeholders in the company are not completely satisfied with the product. Contract and administrative closure are completed、 The stakeholders ask the project manager for performing the minor changes. What should the next activity be for the project manager ?
A、Request a change order to evaluate changes.
B、 Perform a risk analysis to determine impact on the project.
C、 Develop product a post implementation audit.
D、 Record the stakeholders’ feedback and register an issue.