91成人精品一区在线播放,成人毛片在线播放器,国产精品剧情av,日韩尤物在线,亚洲麻豆视频,岛国免费在线,亚洲a欧美

軟題庫 移動APP 掃碼下載APP 隨時隨地移動學習 培訓課程
試卷名稱 信息系統(tǒng)項目管理師-pmp練習題-1
考試中心《信息系統(tǒng)項目管理師-pmp練習題-1》在線考試
試卷年份2017年下半年
試題題型【單選題】
試題內(nèi)容

The project has an earned value (EV) of US$1,530, and a planned value (PV) of US$1,630. A team member suggests
removing a   deliverable to benefit the schedule and positive impact the critical path. After documenting the details, the project manager proceeds?
A. Submit a change request
B. Change the project management plan
C. Recalculate the PV
D. Perform a reserve analysis


相關試題

推薦文章
合作網(wǎng)站內(nèi)容