A project manager is called to an informal meeting with the customer and a problem is raised. This problem has major implications for the project manager’s company, but the customer wants to pursue a solutionat the meeting, The project manager should( ).
A.Tell the customer that he will not address any problems
B.Tell the customer that the problem is not sufficiently defined to company to a solution
C.Collect as much information on the problem without committing hiscompany to a solution
D.Give the customer a range of solutions that might be acceptable to his company
查看答案
試題參考答案:C
試題解析與討論:www.shc2b.com/st/1017351.html
試題2
某項目利潤分析表如下所示:
假設(shè)貼現(xiàn)率為10%,則第一年的利潤凈現(xiàn)值為( )。
A. 1100
B. 10000
C. 11000
D. 12100
查看答案
試題參考答案:B
試題解析與討論:www.shc2b.com/st/43291491.html
試題3
關(guān)于項目招投標的說法,不正確的是()。查看答案
試題參考答案:A
試題解析與討論:www.shc2b.com/st/3888328984.html
試題4
下列關(guān)于電子信息機房的設(shè)計中, ( )不符合《電子信息系統(tǒng)機房設(shè)計規(guī)范GB50174-2008》的要求。
A.機房采用二級、三級耐火等級的建筑材料,重要部位采用一級耐火等級的材料
B. 機房所有設(shè)備的金屬外殼、各類金屬管道、金屬線糟、建筑物金屬結(jié)構(gòu)等結(jié)構(gòu)等全部進行電位連接并接地
C.在機房吊頂上和活動地板下都設(shè)置火災(zāi)探測器
D.主機房內(nèi)絕緣體的靜電電位不大于1KV
查看答案
試題參考答案:A
試題解析與討論:www.shc2b.com/st/894308.html
試題5
用于顯示運行的處理節(jié)點以及居于其上的構(gòu)件、進程和對象的配置的圖是( )。
A.用例圖
B.部署圖
C.類圖
D.構(gòu)件圖
查看答案
試題參考答案:B
試題解析與討論:www.shc2b.com/st/2821972.html
試題6
()的項目不適合使用總價合同。查看答案
試題參考答案:C
試題解析與討論:www.shc2b.com/st/4106225231.html
試題7
在信息系統(tǒng)建設(shè)中,建設(shè)方與承建方的合同可用于()
①作為監(jiān)理工作的基本依據(jù) ②規(guī)定總監(jiān)工程師的職責 ③確定項目的工期 ④規(guī)定雙方的經(jīng)濟關(guān)系⑤規(guī)定扣除招標公司費用的比例
A、①②③
B、①③④
C、②③④⑤
D、①②③④⑤
查看答案
試題參考答案:B
試題解析與討論:www.shc2b.com/st/1261211139.html
試題8
( ) is a measure of schedule performance expressed as the difference between the earned value and the planned value.查看答案
試題參考答案:A
試題解析與討論:www.shc2b.com/st/4536728405.html
試題9
()includes the process for incorporating the organization's quality policy regarding planning managing and controlling project and product quality requirements in order to meet stakeholders’objectives.查看答案
試題參考答案:D
試題解析與討論:www.shc2b.com/st/519418277.html
試題10
《合同法》規(guī)定,價款或酬金約定不明的,按( )的市場價格履行。
A.訂立合同時訂立地
B.履行合同時訂立地
C.訂立合同時履行地
D.履行合同時履行地
查看答案
試題參考答案:C
試題解析與討論:www.shc2b.com/st/1355467.html
信管網(wǎng)訂閱號
信管網(wǎng)視頻號
信管網(wǎng)抖音號
溫馨提示:因考試政策、內(nèi)容不斷變化與調(diào)整,信管網(wǎng)網(wǎng)站提供的以上信息僅供參考,如有異議,請以權(quán)威部門公布的內(nèi)容為準!
信管網(wǎng)致力于為廣大信管從業(yè)人員、愛好者、大學生提供專業(yè)、高質(zhì)量的課程和服務(wù),解決其考試證書、技能提升和就業(yè)的需求。
信管網(wǎng)軟考課程由信管網(wǎng)依托10年專業(yè)軟考教研傾力打造,教材和資料參編作者和資深講師坐鎮(zhèn),通過深研歷年考試出題規(guī)律與考試大綱,深挖核心知識與高頻考點,為學員考試保駕護航。面授、直播&錄播,多種班型靈活學習,滿足不同學員考證需求,降低課程學習難度,使學習效果事半功倍。
發(fā)表評論 查看完整評論 | |