試題1
項目經(jīng)理聘用一名供應(yīng)商交付關(guān)鍵部件。供應(yīng)商未能按期交付,項目經(jīng)理根據(jù)合同條款提出索賠,供應(yīng)商拒絕接受該索賠。項目經(jīng)理能夠如何解決這種情況?查看答案
試題參考答案:C
試題解析與討論:www.shc2b.com/st/4716125225.html
試題2
A new project has high uncertainly in the cost required for completion.What approach should the project manager use to determine the expected costs?查看答案
試題參考答案:D
試題解析與討論:www.shc2b.com/st/478725983.html
試題3
A project team is working on a project's new approved scope. The regulatory team was integral in providing input that necessitated this change. However,the team discovers that t he regulatory department was not listed as a project stakeholder. What should the project manager do next?查看答案
試題參考答案:B
試題解析與討論:www.shc2b.com/st/4801913934.html
試題4
If the end date of an initial plan is later than the desired date, what is the FIRST action the project manager should consider?查看答案
試題參考答案:B
試題解析與討論:www.shc2b.com/st/4937825968.html
試題5
A control chart shows seven data points in a row on one side of the mean. What should be done?查看答案
試題參考答案:C
試題解析與討論:www.shc2b.com/st/4965113508.html
試題6
一個敏捷團(tuán)隊即將開始項目的第一次迭代來為客戶開發(fā)一個軟件應(yīng)用程序。發(fā)起人要求團(tuán)隊與客戶緊密協(xié)作,以增加項目成功的機會。項目經(jīng)理應(yīng)該鼓勵以下哪一項來支持發(fā)起人的要求?查看答案
試題參考答案:D
試題解析與討論:www.shc2b.com/st/526271993.html
試題7
A project manager wants to identify the causes that product t he large majority of the problems or defects in a project. Which tool should the project manager use to help identify the problem areas?()查看答案
試題參考答案:C
試題解析與討論:www.shc2b.com/st/4972920692.html
試題8
Which at the following techniques is an application of the theory of constraints and is useful when scheduling constrained resources?查看答案
試題參考答案:D
試題解析與討論:www.shc2b.com/st/493796070.html
試題9
敏捷管理專業(yè)人士對項目中高風(fēng)險部分感到擔(dān)憂。敏捷管理專業(yè)人士希望確保風(fēng)險和價值都在解決方案中設(shè)立優(yōu)先級。查看答案
試題參考答案:A
試題解析與討論:www.shc2b.com/st/5311920872.html
試題10
作為指導(dǎo)和管理一個項目的組成部分,項目經(jīng)理必須審查已經(jīng)完成的活動。項目經(jīng)理應(yīng)該首先審查哪份文件?查看答案
試題參考答案:A
試題解析與討論:www.shc2b.com/st/472532136.html
信管網(wǎng)訂閱號
信管網(wǎng)視頻號
信管網(wǎng)抖音號
溫馨提示:因考試政策、內(nèi)容不斷變化與調(diào)整,信管網(wǎng)網(wǎng)站提供的以上信息僅供參考,如有異議,請以權(quán)威部門公布的內(nèi)容為準(zhǔn)!
信管網(wǎng)致力于為廣大信管從業(yè)人員、愛好者、大學(xué)生提供專業(yè)、高質(zhì)量的課程和服務(wù),解決其考試證書、技能提升和就業(yè)的需求。
信管網(wǎng)軟考課程由信管網(wǎng)依托10年專業(yè)軟考教研傾力打造,教材和資料參編作者和資深講師坐鎮(zhèn),通過深研歷年考試出題規(guī)律與考試大綱,深挖核心知識與高頻考點,為學(xué)員考試保駕護(hù)航。面授、直播&錄播,多種班型靈活學(xué)習(xí),滿足不同學(xué)員考證需求,降低課程學(xué)習(xí)難度,使學(xué)習(xí)效果事半功倍。
發(fā)表評論 查看完整評論 | |