In a large-scale project, the project manager decides that transferring a risk to a vendor is the best risks response, during project execution, the project managers learns that the vendor is no longer financial capable of covering the risk due to internal problems, It will take three weeks for a new vendor to be appointed?
在一個大型項目中,項目經(jīng)理決定將風(fēng)險轉(zhuǎn)移給供應(yīng)商是最好的風(fēng)險應(yīng)對措施,在項目執(zhí)行期間,項目經(jīng)理了解到該供應(yīng)商因內(nèi)部問題不再具有財務(wù)能力來承受風(fēng)險,指定新的供應(yīng)商需要三周時間,在新計劃生效之前,項目經(jīng)理應(yīng)該做些什么?A.B.D.A.Update the risk response plan to "avoid" by halting work更新風(fēng)險應(yīng)對計劃,通過停止工作來“規(guī)避”
B.Meet with stakeholders to review the response plan and discuss increase the budget to accommodates the risk與相關(guān)方開會審查風(fēng)險應(yīng)對計劃,并討論增加預(yù)算以適應(yīng)該風(fēng)險
C.Proceed with project work繼續(xù)進行項目工作
D.Review existing safety measures and control and assess the possibility of risk occurring審查現(xiàn)有的安全措施和控制措施,并評估風(fēng)險發(fā)生的可能性
信管網(wǎng)參考答案:B
信管網(wǎng)解析:
B是參考答案??键c監(jiān)督風(fēng)險,實施風(fēng)險應(yīng)對措施無效,制定彈回計劃。B選項比較符合題干描述的場景。參考章節(jié)11.5彈回計劃的描述。
信管網(wǎng)訂閱號
信管網(wǎng)視頻號
信管網(wǎng)抖音號
溫馨提示:因考試政策、內(nèi)容不斷變化與調(diào)整,信管網(wǎng)網(wǎng)站提供的以上信息僅供參考,如有異議,請以權(quán)威部門公布的內(nèi)容為準(zhǔn)!
信管網(wǎng)致力于為廣大信管從業(yè)人員、愛好者、大學(xué)生提供專業(yè)、高質(zhì)量的課程和服務(wù),解決其考試證書、技能提升和就業(yè)的需求。
信管網(wǎng)軟考課程由信管網(wǎng)依托10年專業(yè)軟考教研傾力打造,教材和資料參編作者和資深講師坐鎮(zhèn),通過深研歷年考試出題規(guī)律與考試大綱,深挖核心知識與高頻考點,為學(xué)員考試保駕護航。面授、直播&錄播,多種班型靈活學(xué)習(xí),滿足不同學(xué)員考證需求,降低課程學(xué)習(xí)難度,使學(xué)習(xí)效果事半功倍。
發(fā)表評論 查看完整評論 | |